S U L A W E S I
The location of this MHPP is in a hilly area so there are many rivers with fast flows. This area has quite high rainfall compared to other areas, namely around 2.500-3.000 mm per year. The condition of natural conservation is quite well maintained. These three factors cause this district to have large water energy potential.
Capacity : 2 X 9,8 MW
Catchment area: 100 Km2
Annual rainfall: 2.156 mm
Head: 185 m
Design Flow: 12 m3/s
Estimated energy: 303 Gwh/yr
Location: Sulawesi
MegaHidro.com © 2016 - 2024 - All Rights Reserved